Pole relocation work due to a street alteration (roundabout installation), required adding 3 circuits - at 2 mile long each (69kV and 132k)

Existing 2D Design and manual survey

Preliminary survey: 0.5 day travel + 0.5 day survey

Design each profile: 5 days

Redesign after customer feedback: 5 days

Using Power Lines Pro and Lidar

Preliminary survey: 1 hour

Design entire model: 2 days

Redesign after customer feedback: 2 hours

Outcome

  • 5x faster to complete a design using PLP and LiDAR
  • 80% cost reduction for personnel on the project