Transmission Scoping*

Adding 3 circuits at 2 mile long each (69kV and 132kV)

Using Leading Alternative Transmission Software

The client previously had the following timeline:

  • Preliminary survey: 1-day travel + 2-day survey
  • Design the area: 14 days
  • Redesign after customer feedback: 7 days

Average total time for design: approximately 24 days

Using Power Lines Pro

After introducing PLP, the client's new timeline is as follows:

  • Preliminary survey: 1-day travel + 2-day survey
  • Design entire model: 4 days
  • Redesign after customer feedback: 1 day

Average total time for design: approximately 8 days

Outcome

  • 3x faster to complete designs using PLP
  • ⅔ labor cost reduction for personnel on the project

The visualization in PLP and extensive reporting tools helped stakeholders achieve a better understanding of the design. 

*Power Lines Pro can conduct both transmission & distribution scoping projects.

If you have any specific questions about scoping projects, or are interested in a free trial of Power Lines Pro, we’d be happy to discuss your specific use case - contact us via info@powerlinespro.com